Haldeman Creek MSTU Projects

Bathymetric Survey and Data Review

Humiston and Moore Engineers were retained to provide a Bathymetric Survey of the Haldeman Creek existing conditions. The survey data was used to compare the 2006 /2007 post dredge information with the current conditions. The information was used for discussion to move forward with permitting if dredging is required. As of 5-30-2019 all the field work, data collection and analysis was completed and presented to the Advisory Committee on October 3, 2019 click the link to access the information: Survey and data. Dredging permit was received from the Army Corps of Engineers.