On March 24, 2023, the Board of County Commissioners (BCC), acting in its capacity as the Community Redevelopment Agency (CRA), approved the central boardwalk alignment and directed staff to complete the 100% design plans to construct a pedestrian connection from Bayshore Drive to Sugden Regional Park. This alignment was supported by the Local Redevelopment Advisory Board and the community. Design plans are expected to be completed in the third quarter of 2023. The Board also directed staff to design two parking lots on the property to support users of the boardwalk.
March 24, 2023, PowerPoint Presentation: Item 14.B1 #1 Presentation Staff Presentation
Site Analysis & Conceptual Plan was presented at the January 17, 2023 CRA Public Meeting.